The first order of business was figuring out what tub to put in the space. The old tub was a 60" jetted "drop-in" that, you will recall, (1) didn't have working jets, (2) wasn't properly supported by the framing, and (3) didn't fit into the 57" space--the tub protruded three inches into the closet in the adjoining room. Kendra and I decided we would buy a 54" tub instead, which is harder to find than a standard 60" tub. We finally settled on a 54" tub at Menard's, primarily because it was available without special ordering.
This still left us with a size problem -- a 54" tub to go in a 57" space. The best solution I could think of was to build a three-inch shelf out at the top of the tub. This meant more carpentry (ugh)* but seemed very doable. Since 2x lumber is actually 1.5", that means I just needed to nail a couple 2x8 to the framing to create the shelf. It all seemed very easy, until Kendra mentioned that she'd like to install shower doors in the finished space, instead of a shower curtain. Now, my simple shelf project turned into a new wall projecting three inches out from the old wall. Ugh, more carpentry.
*The reason I say "ugh" is not because I hate carpentry, it's just that I'm really bad at it. Driving a nail usually is a two- or three-take process for me. Which makes me hate carpentry.
I set to work reconstructing the space so that we could set the tub. First, I needed to reinforce the floor joists, which had significant (although not catastrophic) water rot, so I sistered some 2x8s to the existing joists. Underneath the bathroom is crawlspace, which made the work more difficult in that I was flat on my back the whole time, yet also easier in that I didn't need to reach straight over my head to work. Due to the bathroom being located on an exterior wall, I was able to rest one end of the 2x8s on the sill plate, which should make them hold better (I think). After reinforcing the joists, I cut a piece of OSB board to fit the opening in the floor and screwed it to the joists.
After a little bit of framing to correct the hole in the wall the old tub was shoved into, and then installing two 2x8s to create the proper width for the tub alcove, it was time to install the tub. I cut and fastened a 2x4 ledger board on the back wall to support the tub. Then I enlisted Kendra's help to lift the tub into place. It took quite a bit of coaxing, shoving, and pushing, but we finally got the tub set on the floor. I doubt we had a quarter-inch of space to spare. I used some shims to level the tub, and then we were set.
The tub snugly in place. You can see the new framing at both the right and left-hand sides of the tub. |
The cement board was surprisingly easy to work with, although there was some drama along the way. First, I needed to clean up some of the wiring by removing the switch and wires that worked the nonfunctioning jetted tub. In the switch's place, I installed a GFCI outlet, located in the same electrical box as the switch for running the exhaust fan. It doesn't really makes sense to have an outlet in that particular spot, but I didn't know what else to put in the box. I guess this will leave a power source in case we want to put in a 42" TV right across from the toilet.
After the wiring, I called and had Cooter's Plumbing come over and replace some of the old PVC pipe that ran to the tub and shower with PEX pipe. They also installed the new shower valve and made the drain connections. With the wiring and plumbing done, it was time to cover the walls.
I attached 4 mil plastic sheeting on top of the lathe board to act as a waterproof barrier to the framing underneath. I decided to install the cement board on the long wall first, because it would require the least cutting and let me practice my technique before moving on to the more delicate pieces.
One wall down, two to go! |
Yesterday, after a couple weeks of no progress, I was finally able to hang the rest of the cement board. Here are a couple shots; this picture shows a straight-ahead view:
And here is a photo showing the new 3" wall:
As of today, we are almost ready to start tiling. I still need to mortar the cement board joints, and finish the perimeter with joint compound. And we still don't have the tile yet, although it's supposed to come in this week. After two months of no downstairs tub, and I'm guessing 40 hours of labor, we are getting close to finishing this project.
4 comments:
Well, I'm totally impressed! Our projects have been put on hold after seeing Rob's great DIY skills. We had a small electrical problem following Rob's space heater blowing a fuse. After he rebooted the electical box, we found that Sophia's room and the hall bath was still cut off from all electricity. He kept promising to look into it. In the meantime, I was dragging extension cords in and out of there to give her light, tv, whatever. After two weeks of not wanting to step on his toes, I finally decided to check out the situation myself. Sophia's room and the hall bath was amazingly the ONLY switch he didn't flip. It took him another day or so to realize I had fixed the problem for him. So after reading about your remodeling efforts, I would damn near call you a proffesional for hire.
Well even though there were some carpentry set backs, it looks great so far. Great job. I look forward to seeing the tiling.
The tiling has me terrified! It's the last layer, so mistakes can't be covered up by anything--although I suspect that any mistakes I've made so far will show through in the final product. I'm ready to be done and move on to the next project, for sure.
The only thing holding the toilet in place was the front of the toilet and the toilet bowl leaning against the wall.steam sauna shower kit
Post a Comment